Fremont Chiller Project, FREMONT, IN
CLIENT OBJECTIVES
Fremont was seeking to upgrade the chiller service, install new temperature controls, and add new lighting throughout the high school and middle school buildings; install new security systems at all three school buildings and three other administration and facilities buildings; and perform brick work at all three schools in three project stages. They were interested in updates that would make each building more energy efficient.
VALUE DELIVERED
Through ECS Midwest's Guaranteed Savings Plan, Fremont is projected to receive annual savings of $668,839.00 for 10 years, totaling $6,688,390.00.
PROJECT SOLUTIONS
ECS Midwest performed upgrade and retro t services at six Fremont school buildings to meet Fremont’s objective of energy savings. This included:
Project 1:
Fremont Elementary/High School
|
Fremont Elementary School
|
Project 2:
Fremont Elementary School
Project 3:
|
Fremont High School
Fremont High School
|
Client Background
Fremont Schools was a current customer of the Service and Controls side of Havel. They had traditionally seen projects completed through the design-bid-build pro- cess but decided to try the Guaranteed Savings Plan (design-build) for this project. Fremont is a town in Fremont Township, Steuben County, Indiana. The population is 2,138 and the school system services just under 1,000 students. All of the Fremont schools received an “A” rating from the Indiana Department of Education.