ECS_MW_RGB_322k_400.png

What Can We Do For You?

260.487.7900

or contact us by email

facebook-30px.png Youtube-30px.png emcornation.png

  • Home
  • About Us
    • Meet the Team
    • Safety and Quality
    • Sustainability
  • Services
    • Energy Solutions
    • Commissioning / Recommissioning
    • Building Operations Services
    • AMR & AMI
    • Water/Wastewater Treatment Plants
  • Case Studies
    • School Systems
    • Elementary Schools
    • Middle Schools
    • High Schools
    • Colleges / Universities
    • Public / Government
  • Contact
  • Careers
  • Shambaugh & Son

Eastern Howard, GREENTOWN, IN

CLIENT OBJECTIVES

Eastern Howard School Corporation’s objective was to do a multi-phase project of ex- tensive updates and renovations at their elementary school and Jr.-Sr. high school.

VALUE DELIVERED

Through the work performed by ECS Midwest, Eastern Howard School Corporation is projected to receive the following savings from each phase of renovations and updates:

• Phase 1: Annual savings of $184,198.00 for 15 years, totaling $2,762,970.00
• Phase 2: Annual savings of $187,077.00 for 15 years, totaling $2,806,155.00
• Phase 3: Annual savings of $182,544.00 for 15 years, totaling $2,738,160.00
• Phase 4: Annual savings of $182,544.00 for 15 years, totaling $2,738,160.00
• Phase 5: Annual savings of $205,971.00 for 15 years, totaling $3,089,565.00
• Phase 6: Annual savings of $184,253.00 for 15 years, totaling $2,763,795.00
• Phase 7: Annual savings of $208,899.00 for 15 years, totaling $3,133,485.00
• Phase 8: Annual savings of $212,638.00 for 11 years, totaling $2,399,018.00

The total projected savings over 15 years will be $22,371,308.00.

PROJECT SOLUTIONS


    Phase 1: Eastern Elementary School
  • 4-Pipe Heating and Cooling Piping Distribution System
  • Classroom Unit Ventilator Replacement
  • Chiller Installation
  • Boiler Installation
  • Phone System Replacement
  • Building Door Re-keying
  • Domestic Water System Consolidation
    Phase 2: Eastern Jr.-Sr. High School
  • 4-Pipe Heating and Cooling Piping Distribution System
  • Classroom Unit Ventilator Replacement
  • Chiller Installation
  • Boiler Installation
  • Phone System Replacement
  • Natatorium Wall Repairs
  • Building Door Re-keying
    Phase 3: Eastern Elementary School
  • Corridor Ceiling & Lighting Replacement
  • Classroom Unit Ventilator Replacement
  • Commissioning
  • Fire Detection Upgrade
  • Security Camera/Door Access Installation
  • Science Room Renovation
    Phase 4: Eastern Jr.-Sr. High School
  • Corridor Ceiling & Lighting Replacement
  • Classroom Unit Ventilator Replacement
  • Commissioning
  • Fire Detection Upgrade
  • Industrial Arts Room Renovation
    Phase 5: Eastern Elementary School
  • Corridor Ceiling & Lighting Replace- ment
  • Classroom Unit Ventilator Replace- ment
  • Northeast Restroom Upgrades
  • Gymnasium HVAC
  • Administrative Of ce HVAC


  • Domestic Hot Water System Consolidation
  • Kitchen & Cafeteria HVAC
  • Fire Detection Upgrade
  • Gymnasium Lighting Retrofit
    Phase 6: Eastern Jr.-Sr. High School
  • Classroom Unit Ventilator Replacement
  • Library Security Upgrades
  • Security Upgrades
  • Fire Detection Upgrade
  • LED Wallpak Installation
  • Hallway Bulkheads and Exterior Masonry Work
  • Classroom Custom Metal Shelving Installation
  • Industrial Arts Room Renovation

Phase 7: Eastern Jr.-Sr. High School
• Library HVAC
• Comet Restroom Upgrades
• Kitchen Restroom Upgrades
• Cafeteria HVAC Upgrades
• PAC Temperature Controls
• Door Hardware Replacement
• Water Softener Upgrade
• Athletic Of ce HVAC Upgrade
• Administrative Of ce HVAC Upgrade
• Window Replacements
• Kitchen HVAC Upgrade
• Skinny and Athletic Hallway Makeover
• Pool Water Heater Replacement
• Kovert Hawkins Architectural Design
• Skinny Hallway Walkoff Meeting

Phase 8: Eastern Jr.-Sr. High School
• Gymnasium HVAC Upgrades
• Gymnasium Lighting Upgrades
• PE & Varsity Restroom Upgrades
• Gymnasium Lobby HVAC Upgrades
• Surge Protection Upgrades
• Softball ADA Accessibility Improvements
• Eastern Elementary School
• Surge Protection Upgrades


CLIENT BACKGROUND

Eastern Howard School Corporation is located in Greentown, Indiana, which is about ten miles east of Kokomo, Indiana. Eastern Schools is a public school district that serves 1,500 students in Greentown and the eastern section of Howard County. Their mission statement is as follows: “Eastern Howard School Corporation will provide academic, social, and physical opportunities to all students in order to allow them to pursue their fullest potential and to prepare them to be responsible and productive citizens.”

    Project Duration:
  • Phase 1 & 2: April 2012 – April 2013
  • Phase 3 & 4: December 2012 – December 2013
  • Phase 5 & 6: November 2013 – December 2014
  • Phase 7: June 2014 – July 2015
  • Phase 8: November 2015 – May 2016
    Contract Amounts:
  • Phase 1: $1,927,681.78 Phase 2: $1,930,045.42
  • Phase 3: $1,904,900.95
  • Phase 4: $1,904,900.95
  • Phase 5: $1,930,582.00
  • Phase 6: $1,930,582.00
  • Phase 7: $1,896,542.00
  • Phase 8: $1,877,613.00
EDUCATION
K-12 SCHOOLS


OPERATING COMPANY:
ECS Midwest

CLIENT:
Brownsburg Community
School Corporation

PROJECT DURATION:
April 2011 – August 2012

CONTRACT AMOUNT:
$1,281,514.00


cs_value.gif



Design/Build
Bid Build
New Construction
Retrofit/Renovation
Electrical Construction
Mechanical Construction
Facilities Services
Consulting Services
Fire Protection

Case Studies

  • School Systems
    • Adams
    • Batesville
    • Bluffton-Harrison
    • Brownsburg
    • Central Noble
    • Cloverdale
    • Cowan
    • Danville
    • Duneland
    • East Allen
    • Eastern Howard
    • Flat Rock-Hawcreek
    • Fremont Chiller Project
    • Fremont Community Schools
    • Garrett-Keyser-Butler
    • Garrett-Keyser-Butler
    • Liberty-Perry
    • Manchester
    • Mill Creek
    • Monroe Central
    • North Newton
    • Plymouth
    • Mishawaka
    • Shelbyville
    • South Central
    • South Dearborn
    • Taylor
    • Tri-Central
    • Triton
    • Triton
    • Union Township
    • Wabash
  • Elementary Schools
    • Bridgepoint
    • Central Noble
    • Central Noble
    • Christ The King
    • Garrett-Keyser-Butler
    • Garrett-Keyser-Butler
    • Greensburg
    • John Simatovich
    • Lake Ridge
    • Manchester
    • Parkwood
    • Porter Township
    • Southeast Fountain
  • Middle Schools
    • Bluffton
  • High Schools
    • Fountain Central
    • Greensburg
    • Lake Ridge
    • Metropolitan
    • North Daviess
  • Colleges / Universities
    • Glen Oaks
    • Notre Dame
    • Western Michigan
  • Public / Government
    • Blackford County
    • Citilink
    • City of Lafayette
    • City of Marion
    • Henry County
    • Jasper County
    • Whitley County Jail
    • South Chicago Heights
 

EMCOR Construction Services Midwest

  • About Us
  • Services
  • Case Studies
  • Contact

Shambaugh & Son, L.P.
Divisions

  • ASG
  • Dalmatian Fire
  • ECS Midwest
  • EMCOR Services Shambaugh
  • Harroun Fire Protection
  • Havel
  • Northstar Fire Protection of Texas
  • Precision Controls
  • Progressive Pipe Fabricators

EMCOR Group, Inc.

  • About Us
  • Locations
  • Investor Relations
  • Sustainability Efforts
©2023 EMCOR Group Inc.

Privacy Notice  |  CCPA Notice at Collection  |  Sitemap

NYSE: EME