Batesville, BATESVILLE, IN
CLIENT OBJECTIVES
Batesville Community Schools was seeking to upgrade the HVAC, temperature controls, and roofing for their primary school building, which was built in 1989.
VALUE DELIVERED
ECS Midwest installed equipment upgrades and supplied building renovations that resulted in a projected annual savings of $298,587.00 for 10 years for a total projected savings $2,985,870.00.
PROJECT SOLUTIONS
ECS Midwest performed the renovation and upgrades at the Batesville Primary School. Services and products included:
Batesville Primary School
• Classroom Air Handling Unit and Condensing Unit Replacement
• DDC Temperature Controls Upgrade
• Variable Air Volume Box Replacement
• Hot Water Pump Variable Frequency Drives
• Metal Roof Coating
CLIENT BACKGROUND
Batesville Community School Corporation was a rst-time customer for this project. They had always gone through the traditional design-bid-build process but decided to try ECS Midwest's Guaranteed Savings Process (Design-Build). They were very satis ed with the process and the outcome is that they will be doing it again in the future.
Batesville Community School Corporation was recently named one of the Top 10 School Corporations in the State of Indiana. The Batesville Primary School serves students K-2nd grade.